Some more works have been added to the schedule in addition to those already shared in the recent A602 November newsletter. This is as a result of necessary changes to programme to complete some works in advance of the Christmas period.

The additional works include:
• Four-way temporary traffic signals on A602/A119 roundabout, for off-peak hours between 9.30am and 4pm each day, on Thursday 26 November and Friday 27 November. More information can be found here: https://one.network/?117901335
• Closure of C163 Ware Road, between A119/A602 roundabout and Watton House Lodge 24/day from Tuesday 15 December to Thursday 17 December for Affinity Water connection works. More information can be found here: https://one.network/?117903461
• Two-way temporary traffic signals on A602 Ware Road near Heath Mount School 24h/day from Tuesday 15 December to Thursday 17 December for Affinity Water connection works. More information can be found here: https://one.network/?117901386
To make sure you are fully updated, we have summarised the planned works from now until 24 December 2020 below.

–A602/A119 roundabout Thurs 26 Nov & Fri 27 Nov Off-peak daytime (9.30am-4pm) Temporary traffic signals
–Whempstead Road, from A602 Ware Road to Whempstead Lane junction Mon 30 Nov Overnight (8pm – 5am) Road closure
–A602 Ware Road at junction with Sacombe Hill Farm Thurs 3 Dec & Fri 4 Dec Off-peak daytime (9.30am-4pm) Temporary traffic signals
–A602 Ware Road from Whempstead Road to Stoneyhills Sun 6 Dec Day time (7am – 7pm)Road closure – timing of closure to be confirmed
–A602 Ware Road near Heath Mount School Tues 15 Dec to Thurs 17 Dec 24h/day Temporary traffic signals
–C163 Ware Road, between A602/A119 roundabout to Watton House Lodge Tues 15 Dec to Thurs 17 Dec 24h/day Road closure
–Sacombe Pound Ongoing 24h/day Closure; will be reopen by the Christmas break (date to be confirmed)

Our team is working alongside Hertfordshire County Council’s Network Management Team to try and keep traffic disruption during this time to a minimum. We are sorry for any inconvenience these works may cause. Please leave yourself extra time for any journeys.
Where possible we will remove traffic management from the road early if the works are completed sooner than programmed.
For more information on the project visit the dedicated web page: www.hertfordshire.gov.uk/a602

These works are subject to change. Please follow @Herts_Highways on Twitter to be up to date – this is where we publicise any last-minute changes to our road works.